EnjoyThe good thingsOne of the largest water supply project in Malaysia. Got site allowance. Got Project Vehicle. Got Shell Card for Diesel. Got Project hand phone. Got increment.
Work from 8 am to 5 pm Monday to Sat.
New shophouses rented for Consultant site office.
The challengesThe Contractor attitude towards consultant. Contractor not experienced in water supply projects. Office politics.
Contractor always late for submission of RFI forms.
Their Construction Manager not capable enough to lead his site team.
The Directors of Contractor company is not professional in their managing the projects.